Travelers in and out of Kings Grant along Kings Grant Road will have noted the construction fence and equipment now staged in the Triangle property. The City of Virginia Beach gave the contractor its authorization to proceed with the work earlier this month. During December, the contractor will move utilities at the site of the pump station (which is near the intersection of Kings Grant Road and Sunnybrook Lane). This will be followed by installation of temporary services and demolition of the existing building and driveway. Work in the roadway will also begin in December. The big picture looks like this:

Activity Start End
Pump Station Demolition December 15, 2015 February 16, 2016
Below Grade Construction February 15, 2016 June 16, 2016
Pump Station Construction June 16, 2016 December 16, 2016
Construction of New Sewer Main December 15, 2015 April 16, 2016

(Road Work)

Installation of the new sewer main will begin near the pump station and proceed in phases to its tie in to the HRSD main near Virginia Beach Blvd. Please take care while driving near construction area, and pay attention to the presence of heavy equipment, construction workers and temporary road signs.

Click here for the contractor’s master schedule