The contractor chosen by the City to replace the sanitary pump station on Kingston Drive has started work.  Work site perimeter protection (the orange silt barrier) is installed and obvious to residents of the area.  The City provided the following schedule:

Activity                                             Start                                     Complete

Pump Station Demolition             December 15, 2015           January 16, 2016

Below Grade Construction           January 15, 2016                July 16, 1026

Pump Station Construction          July 16, 2016                       November 16, 2016

The contractor will not require an off-site storage area for equipment and materials.  Updates will be provided as available.