The Public Utilities Engineering Division of the City of Virginia Beach provided the KGCL with an update on the progress of construction at the Kingston Drive pump station. The wet weather has been a challenge to overcome, but construction is moving along very well. The contractor set up the temporary pumping equipment, demolished the old pump station building, and is preparing to remove the old sewage wet well. A large crane has been set up at the work site. This will be used to remove the below-grade concrete wet well and drive the sheet piles to create a cofferdam that will allow construction of the new wet well. Neighbors should expect noise when the steel sheet piles are driven into the ground to create the cofferdam. The project is still scheduled to complete in November.